ConstructionPhasePlanDevelopmentfortheBlackmoreGroupMay2017CONSTRUCTIONPHASEHEALTH&SAFETYPLANConstructionof52NrNewDwellingsatLandatChapelHill,LongridgeStatus:1stIssueDateRevised:ConstructionPhasePlanDevelopmentfortheBlackmoreGroupMay2017DOCUMENTCONTROLSHEETIssueDetailIssueNo.PreparedBy:Signed:CheckedBy:SignedBy:Date:0JamesDeanAdrianDale12345678910RevisionHistoryRevisionDescription0Firstissue12345678910ThisHealthandSafetyPlanispreparedinaccordancewiththeConstruction(DesignandManagement)Regulations2015‘ManagingHealth&SafetyinConstruction(L153).Itisaworkingdocumentwhichwillevolveduringthecourseoftheconstructionphase.TheCompanyHealthandSafetyPolicyformspartoftheplanandallconstructionworkwilltakeaccountofitscontents.ItisthePrincipalContractorsintentionthattheprojectisconstructedinsuchawaythatthehazardstothehealthandsafetyofallpersonseitherduringtheconstructionphaseorduringtheuseofthebuildingareeliminatedorreducedasfarasreasonablypractical.AllthoseinvolvedintheprojecthaveadutytocomplywiththeHealthandSafetyPlan.ConstructionPhasePlanDevelopmentfortheBlackmoreGroupMay2017Contents1.0ProjectOverview&ScopeofWorks1.1LocationofSite1.2NamesofParties1.3Duration1.4PurposeoftheCPHSP2.0StatementofHealthandSafetyPrinciplesandObjectivesfortheProject2.1Policy2.2Objectives2.3Responsibility3.0ExistingSiteInformation,Security&Restrictions3.1ExistingSiteInformation3.2SecurityArrangements3.3SiteRestrictions3.4Traffic&DeliveryManagement3.5ProtectionofSurfaces&ExistingFoliage4.0ManagementoftheProject4.1Responsibilities4.2ArrangementsforDirectingandCo-ordinatingWork4.3SubContractorSelectionProcess4.4DesignInformationfromSpecialistContractors4.5PlantandElectricalInspection4.6Complaints5.0LegislationandStandards5.1GeneralStandards5.2TrainingStandards5.3InformationandTrainingforthoseonsite6.0SiteRulesandMonitoringArrangements6.1SiteRules6.2MonitoringArrangements7.0ActivitieswithRiskstoHealth&Safety7.1UseofandContactwithPowerTools7.2WorkingatHeight7.3ManualHandling7.4COSHHConstructionPhasePlanDevelopmentfortheBlackmoreGroupMay20177.5LiveServices7.6NoiseVibrationandDust7.7HotWorks7.8BiologicalHazards7.9ConfinedSpaces7.10Spills7.11ExposuretoUVRadiation7.12ControlofLiftingOperations8.0SafeWorkingProcedures8.1RiskAssessmentsandMethodStatements8.2PersonalProtectiveEquipmentRequirements8.3ConstructionMaterials8.4StorageofMaterialsandWorkEquipment8.5StorageofWasteMaterials8.6ProvisionandUseofTemporaryServices8.7TemporaryStructures8.8PermittoWorkSystem9.0EmergencyProcedures9.1Fire9.2IllHealth10.0ReportingofAccidentsandRIDDOR10.1Accidents10.2RIDDOR11.0FirstAidArrangements12.0WelfareArrangements13.0ConsultationforPeopleOn-Site14.0UnforeseenEventualities15.0InformationforPrincipalDesignersSafetyFile16.0ReviewoftheProjectAppendixAFirePlanConstructionPhasePlanDevelopmentfortheBlackmoreGroupMay20171.0ProjectOverview&ScopeofWorksThisplancoverstheaccess,landscapingandtheerectionof52newbuildresidentialproperties.Theworksaretoconsistof–•SiteSet-upincludingnecessaryCorporateandCDM2015relatedsignage•Theprovisionofwelfarefacilitiesincludingsiteoffice&toiletandalaydownarea•Identificationandmarkingofservices•Groundworkanddrainage•Blockworkandfloorconstruction•Roofconstructionandcoverings•MechanicalandElectrical1st&2ndfix•Plastering•Joinery1st&2ndfix•Decoration•Floorfinishes•Accessroads•Landscaping•SiteClearanc...